Line 6: | Line 6: |
[[Anchor(wps)]] | We agreed that because of illnesses and other project commitments the work packages now look more like this. |
Line 9: | Line 10: |
|| Detailed scheduling and planning || MR || || ||<#8080FF> || || || || Contact users and line-up interviews || MR || || ||<#8080FF> || || || |
|| Detailed scheduling and planning || MR || || ||<#8080FF> No detailed shedule or plan available. || || || || Contact users and line-up interviews || MR || || ||<#8080FF> Mustie has interviewed 1 Classics user. Mustie has tried to contact another user from Classics, to find other users he has contacted the DIAMM project and the BRIDGES project. || || || |
Project meeting
Alun and Mustie met at OUCS on 16th Nov 2006
Work packages
We agreed that because of illnesses and other project commitments the work packages now look more like this.
Task/work package |
Leaders |
September |
October |
November |
December |
January |
|
|
|
|
|
|
|
Detailed scheduling and planning |
MR |
|
|
No detailed shedule or plan available. |
|
|
Contact users and line-up interviews |
MR |
|
|
Mustie has interviewed 1 Classics user. Mustie has tried to contact another user from Classics, to find other users he has contacted the DIAMM project and the BRIDGES project. |
|
|
Analysis of IB usability feedback |
MR |
|
|
|
|
|
Analysis of BVREH usability feedback |
MR, AE |
|
|
|
|
|
Interviewing of selected IB users |
MR, AE |
|
|
|
|
|
Interviewing of selected BVREH users |
MR, AE |
|
|
|
|
|
'Lab' usability tests of BRIDGES |
MR, AE |
|
|
|
|
|
Analysis of usability testsFootNote(Including reaction to failure) |
MR, AE |
|
|
|
|
|
Report writing |
MR, MN |
|
|
|
|
|
Final report |
MR, MN |
|
|
|
|
|
Test-drive the demonstration
Connect to the Gridsphere portal
You can connect to the portal containing the BRIDGES and DyVOSE portlets at: