Differences between revisions 7 and 8
Revision 7 as of 2006-11-17 16:29:21
Size: 1867
Editor: AlunEdwards
Comment:
Revision 8 as of 2006-11-17 16:33:59
Size: 2000
Editor: AlunEdwards
Comment:
Deletions are marked like this. Additions are marked like this.
Line 10: Line 10:
|| Detailed scheduling and planning || MR ||<#8080FF> || || No detailed shedule or plan available. || || ||
|| Contact users and line-up interviews || MR ||<#8080FF> || || Mustie has interviewed 1 Classics user. Mustie has tried to contact another user from Classics, to find other users he has contacted the DIAMM project and the BRIDGES project. || || ||
|| Analysis of IB usability feedback || MR ||<#8080FF> ||<#8080FF> ||  || || ||
|| Analysis of BVREH usability feedback || MR, AE || ||<#8080FF> ||  || || ||
|| Interviewing of selected IB users || MR, AE || ||<#8080FF> || || || ||
|| Interviewing of selected BVREH users || MR, AE || ||<#8080FF> ||<#8080FF> || || ||
|| 'Lab' usability tests of BRIDGES || MR, AE || || ||<#8080FF>  ||<#8080FF> || ||
|| Analysis of usability tests[[FootNote(Including reaction to failure)]] || MR, AE || || ||<#8080FF> ||<#8080FF>  || ||
|| Detailed scheduling and planning || MR ||<#8080FF> || || No detailed schedule plan available. || || ||
|| Contact users and line-up interviews || MR ||<#8080FF> || || Via Ruth Mustie has contacted and interviewed 1 Classics user. (1 other to be contacted). Emails to the DIAMM project and the BRIDGES project have not been answered. || || ||
|| Analysis of IB usability feedback || MR ||<#8080FF> ||<#8080FF> || Mustie to arrange meeting with Matthew Mascord to discover if any data / users available? || tbc || ||
|| Analysis of BVREH usability feedback || MR, AE || ||<#8080FF> ||Mustie is not convinced data available. || tbc || ||
|| Interviewing of selected IB users || MR, AE || ||<#8080FF> || ||tba || ||
|| Interviewing of selected BVREH users || MR, AE || ||<#8080FF> ||<#8080FF> ||tbc || ||
|| 'Lab' usability tests of BRIDGES || MR, AE || || ||<#8080FF> tba ||<#8080FF> tba || ||
|| Analysis of usability tests[[FootNote(Including reaction to failure)]] || MR, AE || || ||<#8080FF> ||<#8080FF> || ||

Project meeting

Alun and Mustie met at OUCS on 16th Nov 2006

Work packages

We agreed that because of illnesses and other project commitments the work packages now look more like this.

Task/work package

Leaders

Sept

Oct

Nov

Dec

Jan

Detailed scheduling and planning

MR

No detailed schedule plan available.

Contact users and line-up interviews

MR

Via Ruth Mustie has contacted and interviewed 1 Classics user. (1 other to be contacted). Emails to the DIAMM project and the BRIDGES project have not been answered.

Analysis of IB usability feedback

MR

Mustie to arrange meeting with Matthew Mascord to discover if any data / users available?

tbc

Analysis of BVREH usability feedback

MR, AE

Mustie is not convinced data available.

tbc

Interviewing of selected IB users

MR, AE

tba

Interviewing of selected BVREH users

MR, AE

tbc

'Lab' usability tests of BRIDGES

MR, AE

tba

tba

Analysis of usability testsFootNote(Including reaction to failure)

MR, AE

Report writing

MR, MN

Final report

MR, MN

Test-drive the demonstration

Connect to the Gridsphere portal

You can connect to the portal containing the BRIDGES and DyVOSE portlets at:

ESPGRIDwiki: Phase2Notes (last edited 2013-05-17 16:26:47 by localhost)