Below is a list of known tasks. This project plan (like all plans) will be revised on a continuous basis.
June
- Daniel, Kang and Howard to agree design of monitoring service and agree completion date
- Kate to submit bIT campaign plan
- Kang, Howard and Lisa to discuss WOL at Liverpool
- Kang, Howard and Adrian to present at ITSS conference
- Robert to set up OUCS gateway using mini-ITX hardware
July
- Kang, Howard, Adrian and Robert to finish all tasks relating to distribution of WOL code (see suggestions from Dominic and Oxcert)
- Re-design project website to encompass ideas from bIT campaign plan
August
September
October
November